G. B. Pastine Airport - Ciampino - Structural and operational refurbishing of the flight infrastructures
Project value: Euro 8.636.502,78
Start of works: 2016, August 12
End of works: 2017, April 9
Expected duration of works: 240 days – 3 phases
Earth movements: 82,000 m3
Sub-foundations:38,500 m3
Asphalt surfacing: 45,000 TONNES (asphalt concrete prepared with pure materials, not recycled)
Main interventions carried out:
milling operations of the worn runway surface; structural / functional refurbishment of the surfacing of runways; remake of the road markings; restore the system to the runway lighting.